The following is the estimated schedule for the various stages of Monument construction in West Hollywood Park in the next three (3) months:
- Site mobilization (e.g., site preparations for construction work) begins in mid-July 2024,
- Demolition (e.g., removal of the grass lawn) occurs in early August through mid-August 2024;
- Excavation begins in late August 2024; and
- Underground utilities installed in mid-September through mid-October 2024.
The current estimated date for completion of the Monument is August 2025.
If you’d like to see what was presented at the City’s Public Hearing on Pre-Construction of the Monument on July 9, including the most recent renderings, the project history, the finishes to be used at the Monument site, and the estimated construction schedule, please click here (you will need to install WeTransfer on your computer or phone, if you don’t already have it).